Unit Testing when using EF Core 2.0 - c#

For the project I am doing in my internship we have to use a repository pattern. Since the project was already using EF Core and I read that there was already repository and unit of work in the underlying implementation. I figured I would just use the EF Core methods directly without implementing repository classes as I wanted to prevent clutter.
Well now I am in a bit of a problem, I can't seem to find much useful information on unit testing when I implement this way. The requirement is a hard requirement, and I required 100% coverage of CRUD functions within my controllers due to the standards of this firm. I found some of the Microsoft Documentation here, here, and the integration testing using SQLite but I still can't seem to figure out unit testing. I did some googling as well and I can't find resources aside from integration testing.
Is there some way I can unit test using EF Core directly, or am I gonna have to make repositories in order to properly unit test this program?

Since you do not have a separate repository, you do not have to unit test your repository; you cannot unit test what you don’t have.
What you would usually test with EF Core would be actual database access. For that, you can use the in-memory database to temporarily set up your database which you can run full tests against. Of course, this is more an integration test than a minimal unit test.
But you should think about this: When you write unit tests, you have to have an actual idea of what you are testing. Just saying “I need unit tests for component X” does not make real sense. Usually, it would be more like “I need unit tests for methods U, W, Y of component X”. So unless you actually have methods with real behavior that you need to test, attempting to write unit tests for the database context just makes no sense.
You only want to unit test things things that you write yourself. If there’s nothing, e.g. because you are using the direct database context functionalities for CRUD, then there’s nothing to test. The EF Core project is already covering their side with unit tests, and you probably don’t want to start unit testing third party code here.

With EF Core you may use InMemoryDatabase, mock data of your DbContext and test your methods against this data.
Repository adds additional abstraction layer and makes testing a bit more transparent, but it is also possible to inject DbContext with mocked data for your unit tests.
Some code to illustrate an idea
Just don't forget to check is InMemoryDatabase was already passed to the context and do not add another provider in that case.
protected override void OnConfiguring(DbContextOptionsBuilder optionsBuilder)
{
if (!optionsBuilder.IsConfigured)
{
optionsBuilder.UseSqlServer("ConnectionString");
}
Tip
If you are using ASP.NET Core, then you should not need this code since your database provider is already configured outside of the context (in Startup.cs).

Related

How to write unit test for service having dependency on other service or database

Sorry if I am asking very basic question,
I have set of web services (developed using .Net WebApi). These services are either business layer or data access layer APIs. These APIs are either dependent on other services or database itself.
I want to write unit test cases for it. I have following questions
As business layer APIs has dependency on data access service or some other service. If I write unit test just to invoke business API then it would invoke data access API. Is this the correct way to write unit test case? or should I inject all dependency object with unit test? I think earlier one would be integration test not unit test.
Should I write unit tests for Data access layer at all? I checked this link (Writing tests for data access code: Unit tests are waste) and it says DAL does not require unit tests. Should I still write tests for data access layer. I think it would be integration test not unit tests?
Question 1:
I would say if you want to do TDD, then it's not the "correct" way, because as you said, you would be performing integration tests. Then again, maybe you don't want to do TDD and integration tests are good enough for you, but to answer the question: this wouldn't be the proper way to **unit-**test your code.
Question 2
I would say it depends what you have in your data access layer. For instance, if you implement repositories, you will probably want to write a few tests.
Save method
You want to make sure that given an entity that you have retrieved from your repository, editing some properties of this entity and persisting the changes will actually save the modifications and not create a new entity. Now: you might think this is an integration test, but it really depends on how well designed your code is. For instance, your repository could be just an extra layer of logic on top of a low-level ORM. In that case, when testing the save method, what you will do is that you will assert that the right methods are called with the right parameters on the ORM service injected in your repository.
Errors and exceptions
While accessing data, it is possible to have problems such as connection to the database being broken, or that the format of the data is not as expected, or deserialization problems. If you want to provide some good error handling and perhaps create custom exceptions and add more information to them depending on the context, then you definitely want to write tests to make sure the corrext information is propagated
on the other hand
If your DAL is just a few classes that wrap a non-mockable ORM, and you don't have any logic in there, then perhaps you don't need tests, but it seems that this doesn't happen too often, you will pretty much always have a bit of logic that can go wrong and that you want to test.

Unit Testing Entity Framework Repository

I am working with TDD and all is going well. When I get to my actual Repository though I don't know how to test this.
Consider the code below - this is what I know I want to write but how do I tackle this in a test first way without doing integration testing.
public class UserDb : IUserDb
{
public void Add(User user)
{
using (var context = new EfContext())
{
context.Users.Add(user);
context.SaveChanges();
}
}
}
The link below by forsvarir is what I want to put as an answer. How I can do that?
http://romiller.com/2012/02/14/testing-with-a-fake-dbcontext/
The usual answer to these kinds of questions is:
Isolate the hard to test dependencies (the EF context)
Provide a fake implementation in your tests to verify the correct behaviour of the SUT
This all makes sense when you have interesting logic to test in your system under test. For your specific case, the repository looks like a very thin abstraction between your clean domain and EF-aware logic. Good, keep 'em that way. This also means that it's not really doing much work. I suggest that you don't bother writing isolated unit tests (wrapping EF DbContext seems like extra work that might not pull its weight).
Note that I'm not saying you shouldn't test this code: I often tend to test these thin repositories using a real database, i.e. through integrated tests. For all the code that uses these repositories however, I'd stick to isolated unit testing by providing fake repositories to the system under test. That way I have coverage on my repository code and test that EF is actually talking to my database in the correct way and all other tests that indirectly use these repositories are nice, isolated and lightning-fast.
What are you hoping to achieve by testing the 3rd party tool? You could mock out the context var fakeContext = A.Fake<IDbContext>(); and then assert that an attempt was made to write to the database. A.CallTo(() => fakeContext.SaveChanges()).MustHaveHappened();
The above example uses FakeItEasy mocking library.

Dependent (Procedural) Unit Testing in Visual Studio 2012

In an MVC4 C# website, we are using Unit Testing to test our code. What we are currently doing is creating a mock database, then testing each layer:
Test the Database - connecting, initializing, load, etc.
Test the code accessing the database
Test the view layer
I want these three categories to be run in order and only if the previous one passed. Is this the right way to go about it? The old way we were doing it was using a Dependency Injection framework was a weird approach to mock testing. We actually created a mock class for each data accessor, which sucks because we have to re implement the logic of each method, and it didn't really add any value because if we made a mistake with the logic the first time, we'll make it a second.
I want these three categories to be run in order and only if the
previous one passed. Is this the right way to go about it?
No. You should be test everything in isolation and because of that any failing data access code should be completely unrelated to the view. So the view unit tests should fail for a completely different reason and because of that you should always run all tests.
In general, tests should run in isolation, and should not depend on any other tests. It seems to me that the view layer still depends on the data access code, but that you only abstracted the layer below. In that case, from the view's perspective, you are mocking an indirect dependency, which makes your unit tests more complex than strictly needed.
The old way we were doing it was using a Dependency Injection
framework was a weird approach to mock testing
I'm not sure if I get this, but it seems as if you were using the DI container inside your unit tests. This is a absolute no-no. Don't clutter your tests with any DI framework. And there's no need to. Just design your classes around the dependency injection principle (expose all dependencies as constructor arguments) and in your test you just manually new up the class under test with fake dependencies -or- when this leads to repetitive code, create a factory method in your test class that creates a new instance of the class under test.
We actually created a mock class for each data accessor, which sucks
I'm not sure, but it sounds as if there's something wrong with your design here. You would normally have a IRepository<T> interface for which you would have multiple implementations, such as a UserRepository : IRepository<User>, and OrderRepository : IRepository<Order>. In your test suite, you will have one generic FakeRespository<T> or InMemoryRepository<T> and you're done. No need to mock many classes here.
Here are two great books you should definitely read:
The Art of Unit Testing
Dependency Injection in .NET
Those books will change your life. And since you'll be reading anyway, do read this book as well (not related to your question, but code be a life changer as well).

Unit testing the repository. NHibernate

I've got NHibernate-based (constructor ISessionFactory injection) generic repository implementation which is stored inside DAL. It implements contract which is stored in `Domain Layer'.
Should I test real repository behavior using SQl CE or should I refactor my application to support agnostic-like (like in Tim Maccharty's book http://www.wrox.com/WileyCDA/WroxTitle/productCd-0470147563,descCd-authorInfo.html) Unit of Work and then give my fake implementation of IUnitOfWorkRepository?
Is it a valid approach to run tests on a local database exposing real repository implementation?
Thanks!
The issue is what your are testing and why. That will answer the question.
If:
I want to test a third party tool
That is, are you testing if NHibernate is working (not a kind of test
I do). Then do whatever it requires, so refactoring not required. Loose yourself.
I want to test how my code interacts with a thrid party tool
Then you are talking about what I like to call a interaction test. Refactoring is required as your more interested in how your using NHiberate than if it works.
I want to test my code
The abstract NHibernate entirely. Do whatever is necessary ... wrapper? Your now back into unit testing.
I want to test my application from a user point of view
I think this is above the scope your talking. But you can use this scope talking about components. So ... hmmm ... worthwhile but not easy. Not a unit test, so you want to instantiate the component/app and run the whole thing as its 'user' does. I call these 'UATs' and usually implement as 'Coded UATs'.
A unit test is testing a unit in isolation. So, no, it's not even a unit test if you're going to the database.
Abstract away and test your repositories with mocked up interfaces.
I think to test the repositories you need to use the actual scenario. Otherwise you don't have any other place to test the database access. Mocking the repositories is not a good practice. Because you don't have any logic which is need to test in the repositories. I think you need to write integration tests which is calling actual repositories to have any benefit from it.

Unit testing rules

My question may appear really stupid for some of you but i have to ask.. Sorry..
I don't really understand principles of unit testing.. How can you test classes of your business classes or Data access layer without modify your database?
I explain, i have a functionality who update a field in a database.. Nothing so amazing..
The Business layer class is instantiated and the method BLL.Update() makes some controls and finally instantiate a DAL class who launch a stored procedure in the database with the correct parameters.
Its works but my question is..
To do unit tests who test the DALayer class i have to impact the database in the tests! To test for example if the value 5 is well passed to the DataBase i have to do that and database's field will be 5 after the test!
So i know normally the system is not impacted by tests so i don't understand how you can do tests without without execute methods..
Tx for answers and excuse my poor English..
I will divide your question into several sub questions because it is hard to answer them together.
Unit testing x Integration testing
When you write unit test you are testing simple unit. That means you are testing single execution path in tested method. You need to avoid testing its dependencies like mentioned database. You usually write simple unit test for each execution path so that you have good code coverage by your tests.
When you write integration test you are testing all layers to see if integration and configuration works. You usually don't write integration test for each execution path because there is to many combination accross all layers.
Testing business classes - unit testing
You need to test your business classes without dependency to DAL and DB. To do that you have to design your BL class so that those dependencies are injected from outside. First you need to define abstract class or interface for DAL and pass that DAL interface as parameter to constructor (another way is to expose setable property on BL class). When you test your BL class you will use another implementation of DAL interface which is not dependent on DB. There are well known test patterns Mock, Stub and Fake which defines how to create and use those dummy implementations. Mocking is also supported by many testing frameworks.
Testing data access layer - integration testing
You need to test your DAL against real DB. You will prepare testing DB with test set of data and you will write your tests to work with that data. Each test will run in its own transaction which will be rolled back at the end so it will not modify initial data set.
Best regards, Ladislav
For the scenario you describe in terms of db interaction, mocking is useful. If you have a chance, take a look at Rhino Mocks
You use Inversion of Control together with a mocking framework, e.g. Rhino Mocks as someone already mentioned
If you are not resorting to mocking and using actual DB in testing then it will be integration testing in layman terms and it's not a unit test anymore. I worked on a project where a dedicated sql .mdf was in source control that was attached to database server using NUnit in [Setup] part of [SetupFixture], similary detached in [TearDown]. This was done everytime NUnit test were performed and could be very time consuming depending upon the SQL code you have as well as size of data can make worse.
Now the catch is the maintenance overhead, you may change the DB scehma during you sprint cycle and at relaease, the change DB script has to be run on all databases used in your development and testing including the one used for integration testing as mentioned above. Not just that, new test data (as someone mentioned above) has to be popoulated for new tables/columns created and likewise, the exisitng data may need to be cleansed as well owing to requirements changes or bug fixes.
This seems to be a task in itself and someone competent in team can take the ownership or if time permits you can integrate the execution of change scripts as part of Continuous Integration if you already implemented one. Still the adding and cleansing the test data need to be taken care of manually.